One on one exclusive financial and tax consultation
Free Practical Information for Going Overseas to Thailand
Analyze the challenges and opportunities of the industry in Thailand
Service Positioning
We provide Chinese manufacturers building factories in Thailand with an integrated China–Thailand service covering everything from company incorporation to pre-production approvals. Registration is not treated as just a business licence: we work backwards from your target start-of-production date and put company incorporation, BOI, the factory licence, equipment import and staff visas on a single schedule, with one team carrying it through to the end. After production starts, bookkeeping and tax filing, BOI compliance and audit follow on without a hand-over gap.
Scope of Services: What Is and Is Not Included
| Handled by Z&X | Not included in this service |
|---|---|
| Company incorporation: name reservation, articles of association, shareholder registration, certificate of incorporation, company seal | Outbound investment filing and foreign-exchange registration in China |
| Registrations: VAT (PP.20), social security, customs import/export registration, accompanied bank account opening | Factory site selection, construction and environmental impact assessment |
| BOI investment promotion application: eligibility and category assessment, application documents, interview preparation | Customs clearance (handled by the customs broker you appoint; Z&X handles import release filings in the BOI system and supports clearance) |
| Post-approval BOI filings: machinery master list, maximum raw material stock and production formulas, import release filings | Government fees, translation, certification and other third-party costs (borne by the company at actual cost) |
| Factory licence: determining the factory category, preparing the application, accompanying the factory inspection | Work visas and work permits for non-BOI companies |
| Foreign staff: visas and work permits for management and technical staff of BOI companies | Any guarantee of BOI approval or bank account approval (subject to review by the authorities and the bank) |
| Overall coordination: a schedule worked back from the production date, weekly progress reports, item-by-item sign-off on a delivery checklist | |
| After production starts: bookkeeping and tax filing, BOI write-off and reporting, annual audit (engaged separately) |
How Z&X Differs from a Standard Registration Service
| Point of comparison | Standard registration service | Z&X |
|---|---|---|
| Where the service ends | Ends once the business licence is issued | Ends when you are able to produce: the factory licence, duty-free machinery import and the arrival of foreign staff are all on the schedule |
| Team background | Mainly company secretarial and agency work | Led by advisers with manufacturing finance backgrounds: Biaoshun Jia, General Manager of the EEC Branch, has 12 years of finance and tax experience, more than ten of them at large manufacturers in Thailand and as CFO of a Chinese listed company; his EEC team has served more than 50 large manufacturers |
| Location | Mostly in Bangkok, far from the factory | EEC Branch opened in Chonburi in 2025, close to the eastern industrial estates |
| Link to BOI | Registration and BOI are handled by different firms, so things fall through the cracks at hand-over | Incorporation, the BOI application, machinery lists, write-off and reporting are handled by the same team; Z&X has completed 100+ BOI projects |
| Link to head office in China | Works only on the Thai side | “Two countries, three firms”: Zhongxin (China) Tax Agents, Zhongxin (Thailand) Accounting and Zhongxin (Thailand) Audit can align with your head office's finance and tax requirements at the same time |
| How progress is delivered | Verbal updates | Parallel schedule plus item-by-item sign-off on a delivery checklist, so every step can be verified (Z&X CODE compliance-growth model) |
Common Concerns of Chinese Manufacturers and How Z&X Addresses Them
| Common concern | How Z&X handles it |
|---|---|
| Will our registration documents (shareholder identities, source of funds, technical and process information) leak? | Four confidentiality measures: ① a non-disclosure agreement is signed together with the engagement; ② each project has a dedicated file, accessible only to project team members; ③ documents are used only for this project's government filings; ④ at the end of the project originals are returned against a checklist, and electronic copies are kept or deleted as agreed |
| We cannot see progress or where things are stuck | A schedule is issued on signing, with the responsible party and deadline for each item; progress is reported weekly, and any delay is explained the same day with a recovery plan |
| Costs exceed the budget | The quotation lists service fees separately from government fees, translation, certification and other third-party costs; third-party costs are settled at actual cost against receipts |
| What if an approval is not granted? | We explain in advance which outcomes depend on review by the authorities; if documents are returned, we promptly explain why and give a correction plan and timeline |
| No one follows up after registration, so compliance breaks down | The same team continues with BOI compliance, bookkeeping, tax filing and audit, with a written hand-over checklist |
| Language barriers with Thai authorities | Chinese-speaking advisers work with you throughout, Thai specialists deal with government agencies, and key documents come with a Chinese explanation |
Which Chinese Manufacturers This Service Fits
| Your situation | What Z&X focuses on |
|---|---|
| Building a factory in Thailand for the first time, with a head office unfamiliar with Thai approvals | Explaining every step in Chinese and providing an overall schedule worked back from the production date |
| Production projects planning to apply for BOI | One team linking incorporation, the BOI application, machinery lists and post-approval compliance |
| Projects located in the Eastern Economic Corridor (Chonburi, Rayong, Chachoengsao) | Close follow-up by the Chonburi EEC Branch |
| Production projects that need to enter local supply chains and pass customer factory audits | Designing the entity, shareholding and finance system from the start to meet customer audit requirements and the standards of a listed company's subsidiary |
Service Process: From Assessment to Start of Production
Assessment → Backward schedule → Incorporation ‖ BOI application → Factory and factory licence → Machinery list filing and import → Staff visas → Production → Tax and BOI compliance
| Step | What Z&X does | What the company provides | Output of this step |
|---|---|---|---|
| 1. Needs assessment | Understand products and processes, investment size, target production date and preferred location; assess BOI eligibility and category, foreign shareholding and registered capital | Project overview, shareholder background, equipment and staffing plans | Assessment: recommended route, decisions to make first, approximate timeline |
| 2. Plan and backward schedule | Work back from the production date across incorporation, BOI, factory, factory licence, equipment import and staff visas | Confirm entity, shareholding and scope of service | Written plan, overall schedule, quotation |
| 3. Incorporation and registrations | Name reservation, registration, accompanied bank account opening, VAT and social security registration, customs registration | Shareholder and director documents, paid-up capital, director present to open the bank account | Business licence and registrations (company registration about 2 weeks) |
| 4. BOI application | Application documents, business plan and financial projections, interview preparation, follow-up on approval | Product and process description, equipment list, staffing plan; responsible person attends the interview | BOI approval and promotion certificate |
| 5. Post-approval filings | Machinery master list (review of a new list can take up to about 60 working days, so it should be filed before the first equipment arrives), raw material and production formula filings | Equipment specifications, arrival plan, raw material usage data | Approved filings, allowing duty-free import shipment by shipment |
| 6. Factory licence | Determine the factory category, prepare documents, accompany the inspection | Factory and equipment ready for inspection | Factory licence (where required, formal production cannot start before it is issued) |
| 7. Staff visas | Position approval, visas and work permits for foreign management and technical staff of BOI companies | Staff documents, arrival dates | Foreign staff working legally |
| 8. Pre-production check and hand-over | Check that all registrations, licences and filings are complete, and hand over documents against the checklist | Sign off the delivery checklist | Complete documents and government receipts |
| 9. After production starts (engaged separately) | Bookkeeping and tax filing, BOI write-off and reporting, annual audit | — | Ongoing compliance |
The above describes typical cases; actual timing follows the project schedule and depends on the authorities' review speed, completeness of documents and project complexity.
What Z&X Delivers to Manufacturers
| Deliverable | Content | See also |
|---|---|---|
| Overall schedule worked back from the production date | Responsible parties and deadlines for incorporation, BOI, factory and factory licence, machinery import and staff visas | This page |
| Incorporation and registrations | Business licence, VAT and social security registration, customs registration, bank account | Company Registration & Approval Services |
| BOI application and post-approval filings | Application documents, machinery master list, raw material filings | BOI Investment Promotion Application Services, BOI End-to-End Compliance Services |
| Factory licence | Application documents, accompanied inspection | Factory License Services |
| Staff visas | Visas and work permits for foreign management and technical staff | Work Visa and Work Permit Services |
| Tax hand-over after production starts | Plan for bookkeeping, tax filing and annual audit | Accounting & Tax Outsourcing Services, Audit Services |
Z&X Manufacturing Service Team
| Member | Position | Role in manufacturing projects |
|---|---|---|
| Biaoshun Jia | General Manager of EEC Branch | Former CFO background at large manufacturers in Thailand and a Chinese listed company; responsible for manufacturing finance systems, BOI practice and cost control |
| Qing Su | BOI Project Lead | 13 years of dedicated BOI experience; responsible for BOI applications and online system filings |
| Lijia Li | General Manager of China | 15 years of China–Thailand cross-border finance, tax and compliance management; responsible for aligning with head office finance and tax requirements in China |
Related Solutions
The Registration and BOI Application Process for Thai Companies is Complex
Deviation in understanding BOI policies and difficulty in implementing preferential policies
Language and cultural differences lead to high communication costs
Difficulties in building a local financial team
FAQ
Should the BOI application be initiated before or after company registration?
If production is scheduled to start in a certain month, what is the latest time to submit the BOI application?
If production is scheduled to commence next year, how should we reverse-engineer the timeline for the feasibility study and project implementation?
Is our project better suited for a trading-based model, leased-factory manufacturing, leased-factory operation with BOI privileges, or a self-constructed factory with BOI?
Are 100% foreign-owned shareholdings permitted in the manufacturing, trading and service sectors respectively?
Will the factory location affect the BOI category and privileges?
Why sort out equipment lists and raw material lists in parallel during the BOI application stage?
Which tax, customs and BOI milestones are most often overlooked before production starts?
BOI Work Visa and Work Permit in Thailand: Steps and Timeline